Keep up to date on the different fundraising opportunities voted in by the community at the 2024 BSCO Fall Community Meeting.

Below you will be able to track the status of the various projects. As more information becomes available, new information will be added. Watch for estimates for the renovations, updates to timelines, and more.

As we progress, the community may be asked to vote again once we have firm numbers. If approved, information about our fundraising goals for each project will be included.

Track Renovation

Site

Survey

Awaiting date for visit and full estimate for the track project.

Race Track

Community Vote

Once final numbers are known, and there is a sense of timeline, the community will be invited to approve moving forward with the project.

Approved

Track Project Fundraising

If the community approves the track project, fundraising will be required.

Update: Beaverton School District has been able to allocate funds towards the BSE track renovation, minimizing the amount of money that BSCO will need to fund-raise. However, since they are contributing the bulk of the funding, they control the timeline.

 

As of March 2025, the start date for the BSE track renovation will be Summer of 2029.

Track Renovation Estimates:

$196,000.00 to widen, repair, and resurface the Bonny Slope Track

  • Beaverton School District will contribute $150,000 from the Facilities Modernization Funds

  • BSCO will need to contribute the balance (currently estimated at $46,000)

Support Hungry Families

Make a donation to the BSE Pantry
by using the QR code  or clicking the
link.

Any donation value makes a difference.

Funds are used to help feed families at Bonny Slope.

BSE Pantry needs your support!.png

Garden
Project

Information coming soon!